Sprint Plan_ Multi-Surface Platform and Oracle Expansion

Date: 2026-04-16
Status: Sprint definition
Owner: Sayan
Reviewers: Sagnik and integration reviewers
Scope: Sequence the implementation so contracts and backend truths land before broad UI divergence.

1. Sprint Goal

Create a safe execution path for the multi-surface expansion by landing shared contracts, schema direction, and ownership boundaries before device-specific implementation fragments.

2. Sprint Milestones

Milestone 1: Orientation and inventory of current truth

  • audit current iPad app
  • audit WebOS modules
  • audit Oracle routes and schema
  • audit inventory corpus and current backend shapes

Milestone 2: Shared contract and schema baseline

  • define shared entities
  • define Oracle template chapter model
  • define inventory ingest contracts
  • define admin auth and role boundaries

Milestone 3: Tablet and phone architecture split

  • finalize iPad residual list
  • define Android tablet parity map
  • define phone edge MVP scope

Milestone 4: Backend route and data readiness

  • extend current backend routes and schema
  • avoid parallel service drift

Milestone 5: Surface implementation starts

  • iPad residual completion
  • Android tablet scaffold
  • phone edge MVP scaffold
  • admin control plane scaffold

3. Mandatory Order

The team should not start with broad mobile UI polish.

Correct order:

  1. contracts
  2. schema
  3. backend routes
  4. tablet parity map
  5. phone edge MVP map
  6. UI implementation

4. Deliverables This Sprint Must Produce

  • filled architectural packet
  • real file ownership map
  • Oracle schema extension plan
  • template book outline
  • inventory ingest plan
  • admin surface plan

5. Known Dependencies

  • inventory source files from Sagnik are still pending
  • communications ingestion provider choices may still need final confirmation
  • Android implementation should not start deep UI work before iPad parity mapping is complete